Bahrain International Airport Modernization Project

Location               Manama, Kingdom of Bahrain

Project value        $1.1 billion

Schedule              2016-2021

Service Provided Schedule Management and Expert Delay Analysis

Developing, maintaining and controlling the Baseline Schedule with 39.000 activities and expert delay analysis services which accomplished an Extension of Time for 528 days in total by the Employer of Bahrain International Airport Modernization Program.

AYCOMA performed schedule management and expert delay analysis of the Bahrain International Airport Modernization Program, the 1.1 Billion US Dollars contract, covers the construction of a state-of-the-art new passenger terminal building, airside and landside works, a central utility complex and 3,500 vehicle capacity multi-storey car park.